The second modular building of TAIF has been implemented
The VDS team has implemented the second modular TAIF building at gas station No. 161 in Kazan!
On June 24, the acceptance of the modular building took place with the participation of the General Director, Director of Network Development and head of sales of related products of the TAIF-NK Gas Station Company. According to the results of the acceptance, the modular building was accepted and put into operation by the Customer.
26.06.24
Yesterday, the VDS team conducted technical training for personnel on the use of engineering systems in the modular building of the TAIF control room.
The third module out of seven is being assembled at the VDS Plant, and we plan to complete the implementation of the 2024 program in September.