The second serial modular building of TAIF has been implemented
Today in Kazan, the VDS team completed the implementation of the second serial modular building with an operator area of 50 m2 TAIF.
Installation work started on Monday – in 4 days, the installation of a modular building on the foundation was carried out, work was carried out on interior and exterior decoration, engineering networks, ventilation and air conditioning, placement of commercial equipment and commissioning. The acceptance of the modular operator building by the Customer of TAIF-NK gas station is scheduled for tomorrow.
15.08.24
At the moment, three modular TAIF buildings from the 2024 program are in production at the VDS Plant. The completion of the annual program (7 modular buildings) is scheduled for September.