Multifunctional Tatneft gas station on the M-12 highway

17.10.2023

 

VDS continues to implement the project of the Tatneft mirror multifunctional highway complex on the M-12 Moscow-Kazan highway. Construction and installation works are completed by 75%.

 

Metal frames of operator buildings and canopies have been installed on two mirrored objects, communications have been connected, fuel dispensers for passenger and heavy-duty vehicles have been installed, and bases for rubber coating of work-out zones have been prepared.

At the moment, the plumbing unit building is being installed and the finishing works of the operator's office buildings are underway. In parallel, work is underway to improve the territory:

• installation of the foundation for the asphalt concrete pavement, the laying of which is scheduled for this week;

• filling of the green zone;

• installation of lighting masts.

 

 

The first car with advertising equipment has arrived at the facility, the start of installation is scheduled for the end of October. Modular mobile cabins will also be installed this week.

 

The implementation of the Tatneft highway complex is proceeding according to the schedule agreed with the Customer.

Previous news
Next news
About VDS
Projects
News
Contacts
Corporate responsibility
Periodicals
4th Montazhnikov lane 9, r.2, Minsk, Belarus
Head Office Address
on the map
Contact Us:
+375 29 644 23 12
+375 44 777 94 38
info@vds.by
Career:
+375 29 169 87 15
Subscribe to the newsletter
Linkedin Youtube Instagram Whatsapp Viber Telegram
Download the VDS project catalog
Go to city.vds.group
About VDS
History
Innovation center
Design Center
Mass production
Corporate responsibility
Construction
Projects
Team
News
Periodicals
Sustainable development policy
City
+375 29 644 23 12
info@vds.by
Проекты компании VDS
This site uses cookies to making navigation, communication and services better for you as a user.
Accept