Multifunctional Tatneft gas station on the M-12 highway
17.10.2023
VDS continues to implement the project of the Tatneft mirror multifunctional highway complex on the M-12 Moscow-Kazan highway. Construction and installation works are completed by 75%.
Metal frames of operator buildings and canopies have been installed on two mirrored objects, communications have been connected, fuel dispensers for passenger and heavy-duty vehicles have been installed, and bases for rubber coating of work-out zones have been prepared.
At the moment, the plumbing unit building is being installed and the finishing works of the operator's office buildings are underway. In parallel, work is underway to improve the territory:
• installation of the foundation for the asphalt concrete pavement, the laying of which is scheduled for this week;
• filling of the green zone;
• installation of lighting masts.
The first car with advertising equipment has arrived at the facility, the start of installation is scheduled for the end of October. Modular mobile cabins will also be installed this week.
The implementation of the Tatneft highway complex is proceeding according to the schedule agreed with the Customer.